Federal Acquisition Regulation Header
a line underlining the words Federal Acquisition Regulation

PART 31--CONTRACT COST PRINCIPLES AND PROCEDURES

Sec.
#Description
31.000 Scope of part.
31.001 Definitions.
31.002 Availability of accounting guide.

Subpart 31.1--Applicability
#Description
31.100 Scope of subpart.
31.101 Objectives.
31.102 Fixed-price contracts.
31.103 Contracts with commercial organizations.
31.104 Contracts with educational institutions.
31.105 Construction and architect-engineer contracts.
31.106 Facilities contracts.
31.106-1 Applicable cost principles.
31.106-2 Exceptions to general rules on allowability and allocability.
31.106-3 Contractor's commercial items.
31.107 Contracts with State, local, and federally recognized Indian tribal governments.
31.108 Contracts with nonprofit organizations.
31.109 Advance agreements.
31.110 Indirect cost rate certification and penalties on unallowable costs.

Subpart 31.2--Contracts with Commercial Organizations
#Description
31.201 General.
31.201-1 Composition of total cost.
31.201-2 Determining allowability.
31.201-3 Determining reasonableness.
31.201-4 Determining allocability.
31.201-5 Credits.
31.201-6 Accounting for unallowable costs.
31.201-7 Construction and architect-engineer contracts.
31.202 Direct costs.
31.203 Indirect costs.
31.204 Application of principles and procedures.
31.205 Selected costs.
31.205-1 Public relations and advertising costs.
31.205-2 [Reserved]
31.205-3 Bad debts.
31.205-4 Bonding costs.
31.205-5 Civil defense costs.
31.205-6 Compensation for personal services.
31.205-7 Contingencies.
31.205-8 Contributions or donations.
31.205-9 [Reserved]
31.205-10 Cost of money.
31.205-11 Depreciation.
31.205-12 Economic planning costs.
31.205-13 Employee morale, health, welfare, food service, and dormitory costs and credits.
31.205-14 Entertainment costs.
31.205-15 Fines, penalties, and mischarging costs.
31.205-16 Gains and losses on disposition or impairment of depreciable property or other capital assets.
31.205-17 Idle facilities and idle capacity costs.
31.205-18 Independent research and development and bid and proposal costs.
31.205-19 Insurance and indemnification.
31.205-20 Interest and other financial costs.
31.205-21 Labor relations costs.
31.205-22 Lobbying and political activity costs.
31.205-23 Losses on other contracts.
31.205-24 Maintenance and repair costs.
31.205-25 Manufacturing and production engineering costs.
31.205-26 Material costs.
31.205-27 Organization costs.
31.205-28 Other business expenses.
31.205-29 Plant protection costs.
31.205-30 Patent costs.
31.205-31 Plant reconversion costs.
31.205-32 Precontract costs.
31.205-33 Professional and consultant service costs.
31.205-34 Recruitment costs.
31.205-35 Relocation costs.
31.205-36 Rental costs.
31.205-37 Royalties and other costs for use of patents.
31.205-38 Selling costs.
31.205-39 Service and warranty costs.
31.205-40 Special tooling and special test equipment costs.
31.205-41 Taxes.
31.205-42 Termination costs.
31.205-43 Trade, business, technical, and professional activity costs.
31.205-44 Training and education costs.
31.205-45 Transportation costs.
31.205-46 Travel costs.
31.205-47 Costs related to legal and other proceedings.
31.205-48 Deferred research and development costs.
31.205-49 Goodwill.
31.205-50 [Reserved]
31.205-51 Costs of alcoholic beverages.
31.205-52 Asset valuations resulting from business combinations.

Subpart 31.3--Contracts with Educational Institutions
# Description
31.301 Purpose.
31.302 General.
31.303 Requirements.

Subparts 31.4 and 31.5--[Reserved]

Subpart 31.6--Contracts with State, Local, and Federally Recognized Indian Tribal Governments
# Description
31.601 Purpose.
31.602 General.
31.603 Requirements.

Subpart 31.7--Contracts with Nonprofit Organizations
# Description
31.701 Purpose.
31.702 General.
31.703 Requirements.

31.000 Scope of part.

This part contains cost principles and procedures for--

(a) The pricing of contracts, subcontracts, and modifications to contracts and subcontracts whenever cost analysis is performed (see 15.404-1(c)), and

(b) The determination, negotiation, or allowance of costs when required by a contract clause.

31.001 Definitions.

"Accrued benefit cost method" means an actuarial cost method under which units of benefit are assigned to each cost accounting period and are valued as they accrue; i.e., based on the services performed by each employee in the period involved. The measure of normal cost under this method for each cost accounting period is the present value of the units of benefit deemed to be credited to employees for service in that period. The measure of the actuarial liability at a plan's inception date is the present value of the units of benefit credited to employees for service prior to that date. (This method is also known as the unit credit cost method.)

"Accumulating costs" means collecting cost data in an organized manner, such as through a system of accounts.

"Actual cash value" means the cost of replacing damaged property with other property of like kind and quality in the physical condition of the property immediately before the damage.

"Actual costs," as used in this part (other than Subpart 31.6), means amounts determined on the basis of costs incurred, as distinguished from forecasted costs. Actual costs include standard costs properly adjusted for applicable variances.

"Actuarial assumption" means a prediction of future conditions affecting pension costs; e.g., mortality rate, employee turnover, compensation levels, pension fund earnings, and changes in values of pension funds assets.

"Actuarial cost method" means a technique which uses actuarial assumptions to measure the present value of future pension benefits and pension fund administrative expenses, and which assigns the cost of such benefits and expenses to cost accounting periods.

"Actuarial gain and loss" means the effect on pension cost resulting from differences between actuarial assumptions and actual experience.

"Actuarial liability" means pension cost attributable, under the actuarial cost method in use, to years before the date of a particular actuarial valuation. As of such date, the actuarial liability represents the excess of the present value of the future benefits and administrative expenses over the present value of future contributions, for the normal cost for all plan participants and beneficiaries. The excess of the actuarial liability over the value of the assets of a pension plan is the unfunded actuarial liability.

"Actuarial valuation" means the determination, as of a specified date, of the normal cost, actuarial liability, value of the assets of a pension fund, and other relevant values for the pension plan.

"Allocate" means to assign an item of cost, or a group of items of cost, to one or more cost objectives. This term includes both direct assignment of cost and the reassignment of a share from an indirect cost pool.

"Business unit" means any segment of an organization, or an entire business organization which is not divided into segments.

"Compensated personal absence" means any absence from work for reasons such as illness, vacation, holidays, jury duty, military training, or personal activities for which an employer pays compensation directly to an employee in accordance with a plan or custom of the employer.

"Cost input" means the cost, except general and administrative (G&A) expenses, which for contract costing purposes is allocable to the production of goods and services during a cost accounting period.

"Cost objective," as used in this part (other than Subpart 31.6), means a function, organizational subdivision, contract, or other work unit for which cost data are desired and for which provision is made to accumulate and measure the cost of processes, products, jobs, capitalized projects, etc.

"Cost of capital committed to facilities" means an imputed cost determined by applying a cost of money rate to facilities capital.

"Deferred compensation" means an award made by an employer to compensate an employee in a future cost accounting period or periods for services rendered in one or more cost accounting periods before the date of the receipt of compensation by the employee. This definition shall not include the amount of year end accruals for salaries, wages, or bonuses that are to be paid within a reasonable period of time after the end of a cost accounting period.

"Defined-benefit pension plan" means a pension plan in which the benefits to be paid, or the basis for determining such benefits, are established in advance and the contributions are intended to provide the stated benefits.

"Defined-contribution pension plan" means a pension plan in which the contributions to be made are established in advance and the benefits are determined thereby.

"Directly associated cost" means any cost which is generated solely as a result of the incurrence of another cost, and which would not have been incurred had the other cost not been incurred.

"Estimating costs" means the process of forecasting a future result in terms of cost, based upon information available at the time.

"Expressly unallowable cost" means a particular item or type of cost which, under the express provisions of an applicable law, regulation, or contract, is specifically named and stated to be unallowable.

"Facilities capital" means the net book value of tangible capital assets and of those intangible capital assets that are subject to amortization.

"Final cost objective," as used in this part (other than Subparts 31.3 and 31.6), means a cost objective that has allocated to it both direct and indirect costs and, in the contractor's accumulation system, is one of the final accumulation points.

"Fiscal year," as used in this part, means the accounting period for which annual financial statements are regularly prepared, generally a period of 12 months, 52 weeks, or 53 weeks.

"Funded pension cost," as used in this part, means the portion of pension costs for a current or prior cost accounting period that has been paid to a funding agency.

"General and administrative (G&A) expense" means any management, financial, and other expense which is incurred by or allocated to a business unit and which is for the general management and administration of the business unit as a whole. G&A expense does not include those management expenses whose beneficial or causal relationship to cost objectives can be more directly measured by a base other than a cost input base representing the total activity of a business unit during a cost accounting period.

"Home office" means an office responsible for directing or managing two or more, but not necessarily all, segments of an organization. It typically establishes policy for, and provides guidance to, the segments in their operations. It usually performs management, supervisory, or administrative functions, and may also perform service functions in support of the operations of the various segments. An organization which has intermediate levels, such as groups, may have several home offices which report to a common home office. An intermediate organization may be both a segment and a home office.

"Immediate-gain actuarial cost method" means any of the several actuarial cost methods under which actuarial gains and losses are included as part of the unfunded actuarial liability of the pension plan, rather than as part of the normal cost of the plan.

"Independent research and development (IR&D) cost" means the cost of effort which is neither sponsored by a grant, nor required in performing a contract, and which falls within any of the following four areas--

(a) Basic research,

(b) Applied research,

(c) Development, and

(d) Systems and other concept formulation studies.

"Indirect cost pools," as used in this part (other than Subparts 31.3 and 31.6), means groupings of incurred costs identified with two or more cost objectives but not identified specifically with any final cost objective.

"Insurance administration expenses" means the contractor's costs of administering an insurance program; e.g., the costs of operating an insurance or risk-management department, processing claims, actuarial fees, and service fees paid to insurance companies, trustees, or technical consultants.

"Intangible capital asset" means an asset that has no physical substance, has more than minimal value, and is expected to be held by an enterprise for continued use or possession beyond the current accounting period for the benefits it yields.

"Job," as used in this part, means a homogeneous cluster of work tasks, the completion of which serves an enduring purpose for the organization. Taken as a whole, the collection of tasks, duties, and responsibilities constitutes the assignment for one or more individuals whose work is of the same nature and is performed at the same skill/responsibility level--as opposed to a position, which is a collection of tasks assigned to a specific individual. Within a job, there may be pay categories which are dependent on the degree of supervision required by the employee while performing assigned tasks which are performed by all persons with the same job.

"Job class of employees," as used in this part, means employees performing in positions within the same job.

"Labor cost at standard" means a preestablished measure of the labor element of cost, computed by multiplying labor-rate standard by labor-time standard.

"Labor market," as used in this part, means a place where individuals exchange their labor for compensation. Labor markets are identified and defined by a combination of the following factors--

(1) Geography,

(2) Education and/or technical background required,

(3) Experience required by the job,

(4) Licensing or certification requirements,

(5) Occupational membership, and

(6) Industry.

"Labor-rate standard" means a preestablished measure, expressed in monetary terms, of the price of labor.

"Labor-time standard" means a preestablished measure, expressed in temporal terms, of the quantity of labor.

"Material cost at standard" means a preestablished measure of the material elements of cost, computed by multiplying material-price standard by material-quantity standard.

"Material-price standard" means a preestablished measure, expressed in monetary terms, of the price of material.

"Material-quantity standard" means a preestablished measure, expressed in physical terms, of the quantity of material.

"Moving average cost" means an inventory costing method under which an average unit cost is computed after each acquisition by adding the cost of the newly acquired units to the cost of the units of inventory on hand and dividing this figure by the new total number of units.

"Normal cost" means the annual cost attributable, under the actuarial cost method in use, to years subsequent to a particular valuation date.

"Original complement of low cost equipment" means a group of items acquired for the initial outfitting of a tangible capital asset or an operational unit, or a new addition to either. The items in the group individually cost less than the minimum amount established by the contractor for capitalization for the classes of assets acquired but in the aggregate they represent a material investment. The group, as a complement, is expected to be held for continued service beyond the current period. Initial outfitting of the unit is completed when the unit is ready and available for normal operations.

"Pay-as-you-go cost method" means a method of recognizing pension cost only when benefits are paid to retired employees or their beneficiaries.

"Pension plan" means a deferred compensation plan established and maintained by one or more employers to provide systematically for the payment of benefits to plan participants after their retirements; provided, that the benefits are paid for life or are payable for life at the option of the employees. Additional benefits such as permanent and total disability and death payments, and survivorship payments to beneficiaries of deceased employees may be an integral part of a pension plan.

"Pension plan participant" means any employee or former employee of an employer or any member or former member of an employee organization, who is or may become eligible to receive a benefit from a pension plan which covers employees of such employer or members of such organization who have satisfied the plan's participation requirements, or whose beneficiaries are receiving or may be eligible to receive any such benefit. A participant whose employment status with the employer has not been terminated is an active participant of the employer's pension plan.

"Pricing" means the process of establishing a reasonable amount or amounts to be paid for supplies or services.

"Profit center," as used in this part (other than Subparts 31.3 and 31.6), means the smallest organizationally independent segment of a company charged by management with profit and loss responsibilities.

"Projected average loss" means the estimated long-term average loss per period for periods of comparable exposure to risk of loss.

"Projected benefit cost method" means any of the several actuarial cost methods which distribute the estimated total cost of all the employees' prospective benefits over a period of years, usually their working careers.

"Proposal" means any offer or other submission used as a basis for pricing a contract, contract modification, or termination settlement or for securing payments thereunder.

"Residual value" means the proceeds, less removal and disposal costs, if any, realized upon disposition of a tangible capital asset. It usually is measured by the net proceeds from the sale or other disposition of the asset, or its fair value if the asset is traded in on another asset. The estimated residual value is a current forecast of the residual value.

"Segment" means one of two or more divisions, product departments, plants, or other subdivisions of an organization reporting directly to a home office, usually identified with responsibility for profit and/or producing a product or service. The term includes Government-owned contractor-operated (GOCO) facilities, and joint ventures and subsidiaries (domestic and foreign) in which the organization has a majority ownership. The term also includes those joint ventures and subsidiaries (domestic and foreign) in which the organization has less than a majority of ownership, but over which it exercises control.

"Self-insurance" means the assumption or retention of the risk of loss by the contractor, whether voluntarily or involuntarily. Self-insurance includes the deductible portion of purchased insurance.

"Self-insurance charge" means a cost which represents the projected average loss under a self-insurance plan.

"Service life" means the period of usefulness of a tangible capital asset (or group of assets) to its current owner. The period may be expressed in units of time or output. The estimated service life of a tangible capital asset (or group of assets) is a current forecast of its service life and is the period over which depreciation cost is to be assigned.

"Spread-gain actuarial cost method" means any of the several projected benefit actuarial cost methods under which actuarial gains and losses are included as part of the current and future normal costs of the pension plan.

"Standard cost" means any cost computed with the use of preestablished measures.

"Tangible capital asset" means an asset that has physical substance, more than minimal value, and is expected to be held by an enterprise for continued use or possession beyond the current accounting period for the services it yields.

"Termination gain or loss" means an actuarial gain or loss resulting from the difference between the assumed and actual rates at which pension plan participants separate from employment for reasons other than retirement, disability, or death.

"Unallowable cost" means any cost which, under the provisions of any pertinent law, regulation, or contract, cannot be included in prices, cost-reimbursements, or settlements under a Government contract to which it is allocable.

"Unfunded pension plan," as used in this part, means a defined benefit pension plan for which no funding agency is established for the accumulation of contributions.

"Variance" means the difference between a preestablished measure and an actual measure.

"Weighted average cost" means an inventory costing method under which an average unit cost is computed periodically by dividing the sum of the cost of beginning inventory plus the cost of acquisitions by the total number of units included in these two categories.

31.002 Availability of accounting guide.

Contractors needing assistance in developing or improving their accounting systems and procedures may request a copy of the guide entitled "Guidance for New Contractors" (DCAAP 7641.90). The guide is available from--

Headquarters, Defense Contract Audit Agency

Operating Administrative Office

8725 John J Kingman Road, Suite 2135

Fort Belvoir VA 22060-6219

Telephone No. (703) 767-1066

Telefax No. (703) 767-1061.

Subpart 31.1--Applicability

31.100 Scope of subpart.

This subpart describes the applicability of the cost principles and procedures in succeeding subparts of this part to various types of contracts and subcontracts. It also describes the need for advance agreements.

31.101 Objectives.

In recognition of differing organizational characteristics, the cost principles and procedures in the succeeding subparts are grouped basically by organizational type; e.g., commercial concerns and educational institutions. The overall objective is to provide that, to the extent practicable, all organizations of similar types doing similar work will follow the same cost principles and procedures. To achieve this uniformity, individual deviations concerning cost principles require advance approval of the agency head or designee. Class deviations for the civilian agencies require advance approval of the Civilian Agency Acquisition Council. Class deviations for the National Aeronautics and Space Administration require advance approval of the Associate Administrator for Procurement. Class deviations for the Department of Defense require advance approval of the Director of Defense Procurement, Office of the Under Secretary of Defense for Acquisition and Technology.

31.102 Fixed-price contracts.

The applicable subparts of Part 31 shall be used in the pricing of fixed-price contracts, subcontracts, and modifications to contracts and subcontracts whenever (a) cost analysis is performed, or (b) a fixed-price contract clause requires the determination or negotiation of costs. However, application of cost principles to fixed-price contracts and subcontracts shall not be construed as a requirement to negotiate agreements on individual elements of cost in arriving at agreement on the total price. The final price accepted by the parties reflects agreement only on the total price. Further, notwithstanding the mandatory use of cost principles, the objective will continue to be to negotiate prices that are fair and reasonable, cost and other factors considered.

31.103 Contracts with commercial organizations.

This category includes all contracts and contract modifications for supplies, services, or experimental, developmental, or research work negotiated with organizations other than educational institutions (see 31.104), construction and architect-engineer contracts (see 31.105), State and local governments (see 31.107) and nonprofit organizations (see 31.108) on the basis of cost.

(a) The cost principles and procedures in Subpart 31.2 and agency supplements shall be used in pricing negotiated supply, service, experimental, developmental, and research contracts and contract modifications with commercial organizations whenever cost analysis is performed as required by 15.404-1(c).

(b) In addition, the contracting officer shall incorporate the cost principles and procedures in Subpart 31.2 and agency supplements by reference in contracts with commercial organizations as the basis for--

(1) Determining reimbursable costs under--

(i) Cost-reimbursement contracts and cost-reimbursement subcontracts under these contracts performed by commercial organizations and

(ii) The cost-reimbursement portion of time-and-materials contracts except when material is priced on a basis other than at cost (see 16.601(b)(3));

(2) Negotiating indirect cost rates (see Subpart 42.7);

(3) Proposing, negotiating, or determining costs under terminated contracts (see 49.103 and 49.113);

(4) Price revision of fixed-price incentive contracts (see 16.204 and 16.403);

(5) Price redetermination of price redetermination contracts (see 16.205 and 16.206); and

(6) Pricing changes and other contract modifications.

31.104 Contracts with educational institutions.

This category includes all contracts and contract modifications for research and development, training, and other work performed by educational institutions.

(a) The contracting officer shall incorporate the cost principles and procedures in Subpart 31.3 by reference in cost-reimbursement contracts with educational institutions as the basis for--

(1) Determining reimbursable costs under the contracts and cost-reimbursement subcontracts thereunder performed by educational institutions;

(2) Negotiating indirect cost rates; and

(3) Settling costs of cost-reimbursement terminated contracts (see Subpart 49.3 and 49.109-7).

(b) The cost principles in this subpart are to be used as a guide in evaluating costs in connection with negotiating fixed-price contracts and termination settlements.

31.105 Construction and architect-engineer contracts.

(a) This category includes all contracts and contract modifications negotiated on the basis of cost with organizations other than educational institutions (see 31.104), State and local governments (see 31.107), and nonprofit organizations except those exempted under OMB Circular A-122 (see 31.108) for construction management or construction, alteration or repair of buildings, bridges, roads, or other kinds of real property. It also includes architect-engineer contracts related to construction projects. It does not include contracts for vessels, aircraft, or other kinds of personal property.

(b) Except as otherwise provided in (d) below, the cost principles and procedures in Subpart 31.2 shall be used in the pricing of contracts and contract modifications in this category if cost analysis is performed as required by 15.404-1(c).

(c) In addition, the contracting officer shall incorporate the cost principles and procedures in Subpart 31.2 (as modified by (d) below by reference in contracts in this category as the basis for--

(1) Determining reimbursable costs under cost-reimbursement contracts, including cost-reimbursement subcontracts thereunder;

(2) Negotiating indirect cost rates;

(3) Proposing, negotiating, or determining costs under terminated contracts;

(4) Price revision of fixed-price incentive contracts; and

(5) Pricing changes and other contract modifications.

(d) Except as otherwise provided in this paragraph (d), the allowability of costs for construction and architect-engineer contracts shall be determined in accordance with Subpart 31.2.

(1) Because of widely varying factors such as the nature, size, duration, and location of the construction project, advance agreements as set forth in 31.109, for such items as home office overhead, partners' compensation, employment of consultants, and equipment usage costs, are particularly important in construction and architect-engineer contracts. When appropriate, they serve to express the parties' understanding and avoid possible subsequent disputes or disallowances.

(2) "Construction equipment," as used in this section, means equipment (including marine equipment) in sound workable condition, either owned or controlled by the contractor or the subcontractor at any tier, or obtained from a commercial rental source, and furnished for use under Government contracts.

(i) Allowable ownership and operating costs shall be determined as follows:

(A) Actual cost data shall be used when such data can be determined for both ownership and operations costs for each piece of equipment, or groups of similar serial or series equipment, from the contractor's accounting records. When such costs cannot be so determined, the contracting agency may specify the use of a particular schedule of predetermined rates or any part thereof to determine ownership and operating costs of construction equipment (see subdivisions (d)(2)(i)(B) and (C) of this section). However, costs otherwise unallowable under this part shall not become allowable through the use of any schedule (see 31.109(c)). For example, schedules need to be adjusted for Government contract costing purposes if they are based on replacement cost, include unallowable interest costs, or use improper cost of money rates or computations. Contracting officers should review the computations and factors included within the specified schedule and ensure that unallowable or unacceptably computed factors are not allowed in cost submissions.

(B) Predetermined schedules of construction equipment use rates (e.g., the Construction Equipment Ownership and Operating Expense Schedule, published by the U.S. Army Corps of Engineers, industry sponsored construction equipment cost guides, or commercially published schedules of construction equipment use cost) provide average ownership and operating rates for construction equipment. The allowance for operating costs may include costs for such items as fuel, filters, oil, and grease; servicing, repairs, and maintenance; and tire wear and repair. Costs of labor, mobilization, demobilization, overhead, and profit are generally not reflected in schedules, and separate consideration may be necessary.

(C) When a schedule of predetermined use rates for construction equipment is used to determine direct costs, all costs of equipment that are included in the cost allowances provided by the schedule shall be identified and eliminated from the contractor's other direct and indirect costs charged to the contract. If the contractor's accounting system provides for site or home office overhead allocations, all costs which are included in the equipment allowances may need to be included in any cost input base before computing the contractor's overhead rate. In periods of suspension of work pursuant to a contract clause, the allowance for equipment ownership shall not exceed an amount for standby cost as determined by the schedule or contract provision.

(ii) Reasonable costs of renting construction equipment are allowable (but see paragraph (C) of this subsection).

(A) Costs, such as maintenance and minor or running repairs incident to operating such rented equipment, that are not included in the rental rate are allowable.

(B) Costs incident to major repair and overhaul of rental equipment are unallowable.

(C) The allowability of charges for construction equipment rented from any division, subsidiary, or organization under common control, will be determined in accordance with 31.205-36(b)(3).

(3) Costs incurred at the job site incident to performing the work, such as the cost of superintendence, timekeeping and clerical work, engineering, utility costs, supplies, material handling, restoration and cleanup, etc., are allowable as direct or indirect costs, provided the accounting practice used is in accordance with the contractor's established and consistently followed cost accounting practices for all work.

(4) Rental and any other costs, less any applicable credits incurred in acquiring the temporary use of land, structures, and facilities are allowable. Costs, less any applicable credits, incurred in constructing or fabricating structures and facilities of a temporary nature are allowable.

31.106 Facilities contracts.

31.106-1 Applicable cost principles.

The cost principles and procedures applicable to the evaluation and determination of costs under facilities contracts (as defined in 45.301), and subcontracts thereunder, will be governed by the type of entity to which a facilities contract is awarded. Except as otherwise provided in 31.106-2 of this section, Subpart 31.2 applies to facilities contracts awarded to commercial organizations; Subpart 31.3 applies to facilities contracts awarded to educational institutions; and 31.105 applies to facilities contracts awarded to construction contractors. Whichever cost principles are appropriate will be used in the pricing of facilities contracts and contract modifications if cost analysis is performed as required by 15.404-1(c). In addition, the contracting officer shall incorporate the cost principles and procedures appropriate in the circumstances (e.g., Subpart 31.2; Subpart 31.3; or 31.105) by reference in facilities contracts as the basis for--

(a) Determining reimbursable costs under facilities contracts, including cost-reimbursement subcontracts thereunder;

(b) Negotiating indirect cost rates; and

(c) Determining costs of terminated contracts when the contractor elects to "voucher out" costs (see Subpart 49.3), and for settlement by determination (see 49.109-7).

31.106-2 Exceptions to general rules on allowability and allocability.

(a) A contractor's established accounting system and procedures are normally directed to the equitable allocation of costs to the types of products which the contractor produces or services rendered in the course of normal operating activities. The acquisition of, or work on, facilities for the Government normally does not involve the manufacturing processes, plant departmental operations, cost patterns of work, administrative and managerial control, or clerical effort usual to production of the contractor's normal products or services.

(b) Advance agreements (see 31.109) should be made between the contractor and the contracting officer as to indirect cost items to be applied to the facilities acquisition. A contractor's normal accounting practice for allocating indirect costs to the acquisition of contractor facilities may range from charging all these costs to this acquisition to not charging any. When necessary to produce an equitable result, the contractor's usual method of allocating indirect cost shall be varied, and appropriate adjustment shall be made to the pools of indirect cost and the bases of their distribution.

(c) The purchase of completed facilities (or services in connection with the facilities) from outside sources does not involve the contractor's direct labor or indirect plant maintenance personnel. Accordingly, indirect manufacturing and plant overhead costs, which are primarily incurred or generated by reason of direct labor or maintenance labor operations, are not allocable to the acquisition of such facilities.

(d) Contracts providing for the installation of new facilities or the rehabilitation of existing facilities may involve the use of the contractor's plant maintenance labor, as distinguished from direct labor engaged in the production of the company's normal products. In such instances, only those types of indirect manufacturing and plant operating costs that are related to or incurred by reason of the expenditures of the classes of labor used for the performance of the facilities work may be allocated to the facilities contract. Thus, a facilities contract which involves the use of plant maintenance labor only would not be subject to an allocation of such cost items as direct productive labor supervision, depreciation, and maintenance expense applicable to productive machinery and equipment, or raw material and finished goods storage costs.

(e) Where a facilities contract calls for the construction, production, or rehabilitation of equipment or other items that are involved in the regular course of the contractor's business by the use of the contractor's direct labor and manufacturing processes, the indirect costs normally allocated to all that work may be allocated to the facilities contract.

31.106-3 Contractor's commercial items.

If facilities constituting the contractor's usual commercial items (or only minor modifications thereof) are acquired by the Government under the contract, the Government shall not pay any amount in excess of the contractor's most favored customer price or the price of other suppliers for like quantities of the same or substantially the same items, whichever is lower.

31.107 Contracts with State, local, and federally recognized Indian tribal governments.

(a) Subpart 31.6 provides principles and standards for determining costs applicable to contracts with State, local, and federally recognized Indian tribal governments. They provide the basis for a uniform approach to the problem of determining costs and to promote efficiency and better relationships between State, local, and federally recognized Indian tribal governments, and Federal Government entities. They apply to all programs that involve contracts with State, local, and federally recognized Indian tribal governments, except contracts with--

(1) Publicly financed educational institutions subject to Subpart 31.3; or

(2) Publicly owned hospitals and other providers of medical care subject to requirements promulgated by the sponsoring Government agencies.

(b) The Office of Management and Budget will approve any other exceptions in particular cases when adequate justification is presented.

31.108 Contracts with nonprofit organizations.

Subpart 31.7 provides principles and standards for determining costs applicable to contracts with nonprofit organizations other than educational institutions, State and local governments, and those nonprofit organizations exempted under OMB Circular No. A-122.

31.109 Advance agreements.

(a) The extent of allowability of the costs covered in this part applies broadly to many accounting systems in varying contract situations. Thus, the reasonableness, the allocability and the allowability under the specific cost principles at Subparts 31.2, 31.3, 31.6, and 31.7 of certain costs may be difficult to determine. To avoid possible subsequent disallowance or dispute based on unreasonableness, unallocability or unallowability under the specific cost principles at Subparts 31.2, 31.3, 31.6, and 31.7, contracting officers and contractors should seek advance agreement on the treatment of special or unusual costs. However, an advance agreement is not an absolute requirement and the absence of an advance agreement on any cost will not, in itself, affect the reasonableness, allocability or the allowability under the specific cost principles at Subparts 31.2, 31.3, 31.6, and 31.7 of that cost.

(b) Advance agreements may be negotiated either before or during a contract but should be negotiated before incurrence of the costs involved. The agreements must be in writing, executed by both contracting parties, and incorporated into applicable current and future contracts. An advance agreement shall contain a statement of its applicability and duration.

(c) The contracting officer is not authorized by this 31.109 to agree to a treatment of costs inconsistent with this part. For example, an advance agreement may not provide that, notwithstanding 31.205-20, interest is allowable.

(d) Advance agreements may be negotiated with a particular contractor for a single contract, a group of contracts, or all the contracts of a contracting office, an agency, or several agencies.

(e) The cognizant administrative contracting officer (ACO), or other contracting officer established in Part 42, shall negotiate advance agreements except that an advance agreement affecting only one contract, or class of contracts from a single contracting office, shall be negotiated by a contracting officer in the contracting office, or an ACO when delegated by the contracting officer. When the negotiation authority is delegated, the ACO shall coordinate the proposed agreement with the contracting officer before executing the advance agreement.

(f) Before negotiating an advance agreement, the Government negotiator shall--

(1) Determine if other contracting offices inside the agency or in other agencies have a significant unliquidated dollar balance in contracts with the same contractor;

(2) Inform any such office or agency of the matters under consideration for negotiation; and

(3) As appropriate, invite the office or agency and the cognizant audit agency to participate in prenegotiation discussions and/or in the subsequent negotiations.

(g) Upon completion of the negotiation, the sponsor shall prepare and distribute to other interested agencies and offices, including the audit agency, copies of the executed agreement and a memorandum providing the information specified in 15.406-3, as applicable.

(h) Examples of costs for which advance agreements may be particularly important are--

(1) Compensation for personal services, including but not limited to allowances for off-site pay, incentive pay, location allowances, hardship pay, cost of living differential, and termination of defined benefit pension plans;

(2) Use charges for fully depreciated assets;

(3) Deferred maintenance costs;

(4) Precontract costs;

(5) Independent research and development and bid and proposal costs;

(6) Royalties and other costs for use of patents;

(7) Selling and distribution costs;

(8) Travel and relocation costs, as related to special or mass personnel movements, as related to travel via contractor-owned, -leased, or -chartered aircraft; or as related to maximum per diem rates;

(9) Costs of idle facilities and idle capacity;

(10) Severance pay to employees on support service contracts;

(11) Plant reconversion;

(12) Professional services (e.g., legal, accounting, and engineering);

(13) General and administrative costs (e.g., corporate, division, or branch allocations) attributable to the general management, supervision, and conduct of the contractor's business as a whole. These costs are particularly significant in construction, job-site, architect-engineer, facilities, and Government-owned contractor operated (GOCO) plant contracts (see 31.203(f));

(14) Costs of construction plant and equipment (see 31.105(d));

(15) Costs of public relations and advertising; and

(16) Training and education costs (see 31.205-44(h)).

31.110 Indirect cost rate certification and penalties on unallowable costs.

(a) Certain contracts require certification of the indirect cost rates proposed for final payment purposes. See 42.703-2 for administrative procedures regarding the certification provisions and the related contract clause prescription.

(b) If unallowable costs are included in final indirect cost settlement proposals, penalties may be assessed. See 42.709 for administrative procedures regarding the penalty assessment provisions and the related contract clause prescription.

Subpart 31.2--Contracts with Commercial Organizations

31.201 General.

31.201-1 Composition of total cost.

(a) The total cost of a contract is the sum of the direct and indirect costs allocable to the contract, incurred or to be incurred, less any allocable credits, plus any allocable cost of money pursuant to 31.205-10. In ascertaining what constitutes a cost, any generally accepted method of determining or estimating costs that is equitable and is consistently applied may be used, including standard costs properly adjusted for applicable variances. See 31.201-2(b) and (c) for Cost Accounting Standards (CAS) requirements.

(b) While the total cost of a contract includes all costs properly allocable to the contract, the allowable costs to the Government are limited to those allocable costs which are allowable pursuant to Part 31 and applicable agency supplements.

31.201-2 Determining allowability.

(a) The factors to be considered in determining whether a cost is allowable include the following:

(1) Reasonableness.

(2) Allocability.

(3) Standards promulgated by the CAS Board, if applicable; otherwise, generally accepted accounting principles and practices appropriate to the particular circumstances.

(4) Terms of the contract.

(5) Any limitations set forth in this subpart.

(b) Certain cost principles in this subpart incorporate the measurement, assignment, and allocability rules of selected CAS and limit the allowability of costs to the amounts determined using the criteria in those selected standards. Only those CAS or portions of standards specifically made applicable by the cost principles in this subpart are mandatory unless the contract is CAS-covered (see Part 30). Business units that are not otherwise subject to these standards under a CAS clause are subject to the selected standards only for the purpose of determining allowability of costs on Government contracts. Including the selected standards in the cost principles does not subject the business unit to any other CAS rules and regulations. The applicability of the CAS rules and regulations is determined by the CAS clause, if any, in the contract and the requirements of the standards themselves.

(c) When contractor accounting practices are inconsistent with this Subpart 31.2, costs resulting from such inconsistent practices shall not be allowed in excess of the amount that would have resulted from using practices consistent with this subpart.

(d) A contractor is responsible for accounting for costs appropriately and for maintaining records, including supporting documentation, adequate to demonstrate that costs claimed have been incurred, are allocable to the contract, and comply with applicable cost principles in this subpart and agency supplements. The contracting officer may disallow all or part of a claimed cost which is inadequately supported.

31.201-3 Determining reasonableness.

(a) A cost is reasonable if, in its nature and amount, it does not exceed that which would be incurred by a prudent person in the conduct of competitive business. Reasonableness of specific costs must be examined with particular care in connection with firms or their separate divisions that may not be subject to effective competitive restraints. No presumption of reasonableness shall be attached to the incurrence of costs by a contractor. If an initial review of the facts results in a challenge of a specific cost by the contracting officer or the contracting officer's representative, the burden of proof shall be upon the contractor to establish that such cost is reasonable.

(b) What is reasonable depends upon a variety of considerations and circumstances, including--

(1) Whether it is the type of cost generally recognized as ordinary and necessary for the conduct of the contractor's business or the contract performance;

(2) Generally accepted sound business practices, arm's-length bargaining, and Federal and State laws and regulations;

(3) The contractor's responsibilities to the Government, other customers, the owners of the business, employees, and the public at large; and

(4) Any significant deviations from the contractor's established practices.

31.201-4 Determining allocability.

A cost is allocable if it is assignable or chargeable to one or more cost objectives on the basis of relative benefits received or other equitable relationship. Subject to the foregoing, a cost is allocable to a Government contract if it--

(a) Is incurred specifically for the contract;

(b) Benefits both the contract and other work, and can be distributed to them in reasonable proportion to the benefits received; or

(c) Is necessary to the overall operation of the business, although a direct relationship to any particular cost objective cannot be shown.

31.201-5 Credits.

The applicable portion of any income, rebate, allowance, or other credit relating to any allowable cost and received by or accruing to the contractor shall be credited to the Government either as a cost reduction or by cash refund. See 31.205-6(j)(4) for rules related to refund or credit to the Government upon termination of an over-funded defined benefit pension plan.

31.201-6 Accounting for unallowable costs.

(a) Costs that are expressly unallowable or mutually agreed to be unallowable, including mutually agreed to be unallowable directly associated costs, shall be identified and excluded from any billing, claim, or proposal applicable to a Government contract. A directly associated cost is any cost which is generated solely as a result of incurring another cost, and which would not have been incurred had the other cost not been incurred. When an unallowable cost is incurred, its directly associated costs are also unallowable.

(b) Costs which specifically become designated as unallowable or as unallowable directly associated costs of unallowable costs as a result of a written decision furnished by a contracting officer shall be identified if included in or used in computing any billing, claim, or proposal applicable to a Government contract. This identification requirement applies also to any costs incurred for the same purpose under like circumstances as the costs specifically identified as unallowable under either this paragraph or paragraph (a) above.

(c) The practices for accounting for and presentation of unallowable costs will be those as described in 48 CFR 9904.405, Accounting for Unallowable Costs.

(d) If a directly associated cost is included in a cost pool which is allocated over a base that includes the unallowable cost with which it is associated, the directly associated cost shall remain in the cost pool. Since the unallowable costs will attract their allocable share of costs from the cost pool, no further action is required to assure disallowance of the directly associated costs. In all other cases, the directly associated costs, if material in amount, must be purged from the cost pool as unallowable costs.

(e)(1) In determining the materiality of a directly associated cost, consideration should be given to the significance of--

(i) The actual dollar amount,

(ii) The cumulative effect of all directly associated costs in a cost pool, or

(iii) The ultimate effect on the cost of Government contracts.

(2) Salary expenses of employees who participate in activities that generate unallowable costs shall be treated as directly associated costs to the extent of the time spent on the proscribed activity, provided the costs are material in accordance with subparagraph (e)(1) above (except when such salary expenses are, themselves, unallowable). The time spent in proscribed activities should be compared to total time spent on company activities to determine if the costs are material. Time spent by employees outside the normal working hours should not be considered except when it is evident that an employee engages so frequently in company activities during periods outside normal working hours as to indicate that such activities are a part of the employee's regular duties.

(3) When a selected item of cost under 31.205 provides that directly associated costs be unallowable, it is intended that such directly associated costs be unallowable only if determined to be material in amount in accordance with the criteria provided in subparagraphs (e)(1) and (e)(2) of this section, except in those situations where allowance of any of the directly associated costs involved would be considered to be contrary to public policy.

31.201-7 Construction and architect-engineer contracts.

Specific principles and procedures for evaluating and determining costs in connection with contracts and subcontracts for construction, and architect-engineer contracts related to construction projects, are in 31.105. The applicability of these principles and procedures is set forth in 31.000 and 31.100.

31.202 Direct costs.

(a) A direct cost is any cost that can be identified specifically with a particular final cost objective. No final cost objective shall have allocated to it as a direct cost any cost, if other costs incurred for the same purpose in like circumstances have been included in any indirect cost pool to be allocated to that or any other final cost objective. Costs identified specifically with the contract are direct costs of the contract and are to be charged directly to the contract. All costs specifically identified with other final cost objectives of the contractor are direct costs of those cost objectives and are not to be charged to the contract directly or indirectly.

(b) For reasons of practicality, any direct cost of minor dollar amount may be treated as an indirect cost if the accounting treatment--

(1) Is consistently applied to all final cost objectives; and

(2) Produces substantially the same results as treating the cost as a direct cost.

31.203 Indirect costs.

(a) An indirect cost is any cost not directly identified with a single, final cost objective, but identified with two or more final cost objectives or an intermediate cost objective. It is not subject to treatment as a direct cost. After direct costs have been determined and charged directly to the contract or other work, indirect costs are those remaining to be allocated to the several cost objectives. An indirect cost shall not be allocated to a final cost objective if other costs incurred for the same purpose in like circumstances have been included as a direct cost of that or any other final cost objective.

(b) Indirect costs shall be accumulated by logical cost groupings with due consideration of the reasons for incurring such costs. Each grouping should be determined so as to permit distribution of the grouping on the basis of the benefits accruing to the several cost objectives. Commonly, manufacturing overhead, selling expenses, and general and administrative (G&A) expenses are separately grouped. Similarly, the particular case may require subdivision of these groupings, e.g., building occupancy costs might be separable from those of personnel administration within the manufacturing overhead group. This necessitates selecting a distribution base common to all cost objectives to which the grouping is to be allocated. The base should be selected so as to permit allocation of the grouping on the basis of the benefits accruing to the several cost objectives. When substantially the same results can be achieved through less precise methods, the number and composition of cost groupings should be governed by practical considerations and should not unduly complicate the allocation.

(c) Once an appropriate base for distributing indirect costs has been accepted, it shall not be fragmented by removing individual elements. All items properly includable in an indirect cost base should bear a pro rata share of indirect costs irrespective of their acceptance as Government contract costs. For example, when a cost input base is used for the distribution of G&A costs, all items that would properly be part of the cost input base, whether allowable or unallowable, shall be included in the base and bear their pro rata share of G&A costs.

(d) The contractor's method of allocating indirect costs shall be in accordance with standards promulgated by the CAS Board, if applicable to the contract; otherwise, the method shall be in accordance with generally accepted accounting principles which are consistently applied. The method may require examination when--

(1) Substantial differences occur between the cost patterns of work under the contract and the contractor's other work;

(2) Significant changes occur in the nature of the business, the extent of subcontracting, fixed-asset improvement programs, inventories, the volume of sales and production, manufacturing processes, the contractor's products, or other relevant circumstances; or

(3) Indirect cost groupings developed for a contractor's primary location are applied to offsite locations. Separate cost groupings for costs allocable to offsite locations may be necessary to permit equitable distribution of costs on the basis of the benefits accruing to the several cost objectives.

(e) A base period for allocating indirect costs is the cost accounting period during which such costs are incurred and accumulated for distribution to work performed in that period. The criteria and guidance in 30.406 for selecting the cost accounting periods to be used in allocating indirect costs are incorporated herein for application to contracts subject to full CAS coverage. For contracts subject to modified CAS coverage and for non-CAS-covered contracts, the base period for allocating indirect costs will normally be the contractor's fiscal year. But a shorter period may be appropriate (1) for contracts in which performance involves only a minor portion of the fiscal year, or (2) when it is general practice in the industry to use a shorter period. When a contract is performed over an extended period, as many base periods shall be used as are required to represent the period of contract performance.

(f) Special care should be exercised in applying the principles of paragraphs (b), (c), and (d) above when Government-owned contractor-operated (GOCO) plants are involved. The distribution of corporate, division, or branch office G&A expenses to such plants operating with little or no dependence on corporate administrative activities may require more precise cost groupings, detailed accounts screening, and carefully developed distribution bases.

31.204 Application of principles and procedures.

(a) Costs shall be allowed to the extent they are reasonable, allocable, and determined to be allowable under 31.201, 31.202, 31.203, and 31.205. These criteria apply to all of the selected items that follow, even if particular guidance is provided for certain items for emphasis or clarity.

(b) Costs incurred as reimbursements or payments to a subcontractor under a cost-reimbursement, fixed-price incentive, or price redeterminable type subcontract of any tier above the first firm-fixed-price subcontract or fixed-price subcontract with economic price adjustment provisions are allowable to the extent that allowance is consistent with the appropriate subpart of this Part 31 applicable to the subcontract involved. Costs incurred as payments under firm-fixed-price subcontracts or fixed-price subcontracts with economic price adjustment provisions or modifications thereto, when cost analysis was performed under 15.404-1(c), shall be allowable only to the extent that the price was negotiated in accordance with 31.102.

(c) Section 31.205 does not cover every element of cost. Failure to include any item of cost does not imply that it is either allowable or unallowable. The determination of allowability shall be based on the principles and standards in this subpart and the treatment of similar or related selected items. When more than one subsection in 31.205 is relevant to a contractor cost, the cost shall be apportioned among the applicable subsections, and the determination of allowability of each portion shall be based on the guidance contained in the applicable subsection. When a cost, to which more than one subsection in 31.205 is relevant, cannot be apportioned, the determination of allowability shall be based on the guidance contained in the subsection that most specifically deals with, or best captures the essential nature of, the cost at issue.

31.205 Selected costs.

31.205-1 Public relations and advertising costs.

(a) "Public relations" means all functions and activities dedicated to--

(1) Maintaining, protecting, and enhancing the image of a concern or its products; or

(2) Maintaining or promoting reciprocal understanding and favorable relations with the public at large, or any segment of the public. The term public relations includes activities associated with areas such as advertising, customer relations, etc.

(b) "Advertising" means the use of media to promote the sale of products or services and to accomplish the activities referred to in paragraph (d) of this subsection, regardless of the medium employed, when the advertiser has control over the form and content of what will appear, the media in which it will appear, and when it will appear. Advertising media include but are not limited to conventions, exhibits, free goods, samples, magazines, newspapers, trade papers, direct mail, dealer cards, window displays, outdoor advertising, radio, and television.

(c) Public relations and advertising costs include the costs of media time and space, purchased services performed by outside organizations, as well as the applicable portion of salaries, travel, and fringe benefits of employees engaged in the functions and activities identified in paragraphs (a) and (b) of this subsection.

(d) The only allowable advertising costs are those that are--

(1) Specifically required by contract, or that arise from requirements of Government contracts and that are exclusively for--

(i) Recruiting personnel required for performing contractual obligations, when considered in conjunction with all other recruitment costs (but see 31.205-34);

(ii) Acquiring scarce items for contract performance; or

(iii) Disposing of scrap or surplus materials acquired for contract performance.

(2) Costs of activities to promote sales of products normally sold to the U.S. Government, including trade shows, which contain a significant effort to promote exports from the United States. Such costs are allowable, notwithstanding subparagraphs (f)(1), (f)(3), (f)(4)(ii), and (f)(5) of this subsection. However, such costs do not include the costs of memorabilia (e.g., models, gifts, and souvenirs), alcoholic beverages, entertainment, and physical facilities which are primarily used for entertainment rather than product promotion.

(e) Allowable public relations costs include the following:

(1) Costs specifically required by contract.

(2) Costs of--

(i) Responding to inquiries on company policies and activities;

(ii) Communicating with the public, press, stockholders, creditors, and customers; and

(iii) Conducting general liaison with news media and Government public relations officers, to the extent that such activities are limited to communication and liaison necessary to keep the public informed on matters of public concern such as notice of contract awards, plant closings or openings, employee layoffs or rehires, financial information, etc.

(3) Costs of participation in community service activities (e.g., blood bank drives, charity drives, savings bond drives, disaster assistance, etc.).

(4) Costs of plant tours and open houses (but see subparagraph (f)(5) of this subsection).

(5) Costs of keel laying, ship launching, commissioning, and roll-out ceremonies, to the extent specifically provided for by contract.

(f) Unallowable public relations and advertising costs include the following:

(1) All public relations and advertising costs, other than those specified in paragraphs (d) and (e) of this subsection, whose primary purpose is to promote the sale of products or services by stimulating interest in a product or product line (except for those costs made allowable under 31.205-38(c)), or by disseminating messages calling favorable attention to the contractor for purposes of enhancing the company image to sell the company's products or services.

(2) All costs of trade shows and other special events which do not contain a significant effort to promote the export sales of products normally sold to the U.S. Government.

(3) Costs of sponsoring meetings, conventions, symposia, seminars, and other special events when the principal purpose of the event is other than dissemination of technical information or stimulation of production.

(4) Costs of ceremonies such as--

(i) Corporate celebrations and

(ii) New product announcements.

(5) Costs of promotional material, motion pictures, videotapes, brochures, handouts, magazines, and other media that are designed to call favorable attention to the contractor and its activities.

(6) Costs of souvenirs, models, imprinted clothing, buttons, and other mementos provided to customers or the public.

(7) Costs of memberships in civic and community organizations.

31.205-2 [Reserved]

31.205-3 Bad debts.

Bad debts, including actual or estimated losses arising from uncollectible accounts receivable due from customers and other claims, and any directly associated costs such as collection costs, and legal costs are unallowable.

31.205-4 Bonding costs.

(a) Bonding costs arise when the Government requires assurance against financial loss to itself or others by reason of the act or default of the contractor. They arise also in instances where the contractor requires similar assurance. Included are such bonds as bid, performance, payment, advance payment, infringement, and fidelity bonds.

(b) Costs of bonding required pursuant to the terms of the contract are allowable.

(c) Costs of bonding required by the contractor in the general conduct of its business are allowable to the extent that such bonding is in accordance with sound business practice and the rates and premiums are reasonable under the circumstances.

31.205-5 Civil defense costs.

(a) Civil defense costs are those incurred in planning for, and protecting life and property against, the possible effects of enemy attack. Costs of civil defense measures (including costs in excess of normal plant protection costs, first-aid training and supplies, fire fighting training and equipment, posting of additional exit notices and directions, and other approved civil defense measures) undertaken on the contractor's premises pursuant to suggestions or requirements of civil defense authorities are allowable when allocated to all work of the contractor.

(b) Costs of capital assets acquired for civil defense purposes are allowable through depreciation (see 31.205-11).

(c) Contributions to local civil defense funds and projects are unallowable.

31.205-6 Compensation for personal services.

(a) General. Compensation for personal services includes all remuneration paid currently or accrued, in whatever form and whether paid immediately or deferred, for services rendered by employees to the contractor during the period of contract performance (except as otherwise provided for in other paragraphs of this subsection). It includes, but is not limited to, salaries; wages; directors' and executive committee members' fees; bonuses (including stock bonuses); incentive awards; employee stock options, and stock appreciation rights; employee stock ownership plans; employee insurance; fringe benefits; contributions to pension, other postretirement benefits, annuity, and employee incentive compensation plans; and allowances for off-site pay, incentive pay, location allowances, hardship pay, severance pay, and cost of living differential. Compensation for personal services is allowable subject to the following general criteria and additional requirements contained in other parts of this cost principle:

(1) Compensation for personal services must be for work performed by the employee in the current year and must not represent a retroactive adjustment of prior years' salaries or wages (but see 31.205-6(g), (h), (j), (k), (m), and (o) of this subsection).

(2) The compensation in total must be reasonable for the work performed; however, specific restrictions on individual compensation elements must be observed where they are prescribed.

(3) The compensation must be based upon and conform to the terms and conditions of the contractor's established compensation plan or practice followed so consistently as to imply, in effect, an agreement to make the payment.

(4) No presumption of allowability will exist where the contractor introduces major revisions of existing compensation plans or new plans and the contractor--

(i) Has not notified the cognizant ACO of the changes either before their implementation or within a reasonable period after their implementation, and

(ii) Has not provided the Government, either before implementation or within a reasonable period after it, an opportunity to review the allowability of the changes.

(5) Costs that are unallowable under other paragraphs of this Subpart 31.2 shall not be allowable under this subsection 31.205-6 solely on the basis that they constitute compensation for personal services.

(b) Reasonableness. The compensation for personal services paid or accrued to each employee must be reasonable for the work performed. Compensation will be considered reasonable if each of the allowable elements making up the employee's compensation package is reasonable. This paragraph addresses the reasonableness of compensation, except when the compensation is set by provisions of a labor-management agreement under terms of the Federal Labor Relations Act or similar state statutes. The tests for reasonableness of labor-management agreements are set forth in paragraph (c) of this subsection. In addition to the provisions of 31.201-3, in testing the reasonableness of individual elements for particular employees or job classes of employees, consideration should be given to factors determined to be relevant by the contracting officer.

(1) Among others, factors which may be relevant include general conformity with the compensation practices of other firms of the same size, the compensation practices of other firms in the same industry, the compensation practices of firms in the same geographic area, the compensation practices of firms engaged in predominantly non-Government work, and the cost of comparable services obtainable from outside sources. The appropriate factors for evaluating the reasonableness of compensation depend on the degree to which those factors are representative of the labor market for the job being evaluated. The relative significance of factors will vary according to circumstances. In administering this principle, it is recognized that not every compensation case need be subjected in detail to the tests described in this cost principle. The tests need be applied only when a general review reveals amounts or types of compensation that appear unreasonable or unjustified. Based on an initial review of the facts, contracting officers or their representatives may challenge the reasonableness of any individual element or the sum of the individual elements of compensation paid or accrued to particular employees or job classes of employees. In such cases, there is no presumption of reasonableness and, upon challenge, the contractor must demonstrate the reasonableness of the compensation item in question. In doing so, the contractor may introduce, and the contracting officer will consider, not only any circumstances surrounding the compensation item challenged, but also the magnitude of other compensation elements which may be lower than would be considered reasonable in themselves. However, the contractor's right to introduce offsetting compensation elements into consideration is subject to the following limitations:

(i) Offsets will be considered only between the allowable elements of an employee's (or a job class of employees') compensation package or between the compensation packages of employees in jobs within the same job grade or level.

(ii) Offsets will be considered only between the allowable portion of the following compensation elements of employees or job classes of employees:

(A) Wages and salaries.

(B) Incentive bonuses.

(C) Deferred compensation.

(D) Pension and savings plan benefits.

(E) Health insurance benefits.

(F) Life insurance benefits.

(G) Compensated personal absence benefits.

However, any of the above elements or portions thereof, whose amount is not measurable, shall not be introduced or considered as an offset item.

(iii) In considering offsets, the magnitude of the compensation elements in question must be taken into account. In determining the magnitude of compensation elements, the timing of receipt by the employee must be considered.

(2) Compensation costs under certain conditions give rise to the need for special consideration. Among such conditions are the following:

(i) Compensation to (A) owners of closely held corporations, partners, sole proprietors, or members of their immediate families, or (B) persons who are contractually committed to acquire a substantial financial interest in the contractor's enterprise. Determination should be made that salaries are reasonable for the personal services rendered rather than being a distribution of profits. Compensation in lieu of salary for services rendered by partners and sole proprietors will be allowed to the extent that it is reasonable and does not constitute a distribution of profits. For closely held corporations, compensation costs covered by this subdivision shall not be recognized in amounts exceeding those costs that are deductible as compensation under the Internal Revenue Code and regulations under it.

(ii) Any change in a contractor's compensation policy that results in a substantial increase in the contractor's level of compensation, particularly when it was concurrent with an increase in the ratio of Government contracts to other business, or any change in the treatment of allowability of specific types of compensation due to changes in Government policy. Contracting officers or their representatives should normally challenge increased costs where major revisions of existing compensation plans or new plans are introduced by the contractor, and the contractor--

(A) Has not notified the cognizant ACO of the changes either before their implementation or within a reasonable period after their implementation; and

(B) Has not provided the Government, either before implementation or within a reasonable period after it, an opportunity to review the reasonableness of the changes.

(iii) The contractor's business is such that its compensation levels are not subject to the restraints that normally occur in the conduct of competitive business.

(iv) The contractor incurs costs for compensation in excess of the amounts which are deductible under the Internal Revenue Code and regulations issued under it.

(c) Labor-management agreements. If costs of compensation established under "arm's length" negotiated labor-management agreements are otherwise allowable, the costs are reasonable if, as applied to work in performing Government contracts, they are not determined to be unwarranted by the character and circumstances of the work or discriminatory against the Government. The application of the provisions of a labor-management agreement designed to apply to a given set of circumstances and conditions of employment (e.g, work involving extremely hazardous activities or work not requiring recurrent use of overtime) is unwarranted when applied to a Government contract involving significantly different circumstances and conditions of employment (e.g., work involving less hazardous activities or work continually requiring use of overtime). It is discriminatory against the Government if it results in employee compensation (in whatever form or name) in excess of that being paid for similar non-Government work under comparable circumstances. Disallowance of costs will not be made under this paragraph (c) unless--

(1) The contractor has been permitted an opportunity to justify the costs; and

(2) Due consideration has been given to whether unusual conditions pertain to Government contract work, imposing burdens, hardships, or hazards on the contractor's employees, for which compensation that might otherwise appear unreasonable is required to attract and hold necessary personnel.

(d) Form of payment. (1) Compensation for personal services includes compensation paid or to be paid in the future to employees in the form of cash, corporate securities, such as stocks, bonds, and other financial instruments (see paragraph (d)(2) of this subsection regarding valuation), or other assets, products, or services.

(2) When compensation is paid with securities of the contractor or of an affiliate, the following additional restrictions apply:

(i) Valuation placed on the securities shall be the fair market value on the measurement date (i.e., the first date the number of shares awarded is known) determined upon the most objective basis available.

(ii) Accruals for the cost of securities before issuing the securities to the employees shall be subject to adjustment according to the possibilities that the employees will not receive the securities and that their interest in the accruals will be forfeited.

(e) Domestic and foreign differential pay. (1) When personal services are performed in a foreign country, compensation may also include a differential that may properly consider all expenses associated with foreign employment such as housing, cost of living adjustments, transportation, bonuses, additional Federal, State, local or foreign income taxes resulting from foreign assignment, and other related expenses.

(2) Differential allowances for additional Federal, State, or local income taxes resulting from domestic assignments are unallowable.

(f) Bonuses and incentive compensation. (1) Incentive compensation for management employees, cash bonuses, suggestion awards, safety awards, and incentive compensation based on production, cost reduction, or efficient performance are allowable provided the awards are paid or accrued under an agreement entered into in good faith between the contractor and the employees before the services are rendered or pursuant to an established plan or policy followed by the contractor so consistently as to imply, in effect, an agreement to make such payment and the basis for the award is supported.

(2) When the bonus and incentive compensation payments are deferred, the costs are subject to the requirements of subparagraph (f)(1) of this subsection and of paragraph (k) of this subsection.

(g) Severance pay. (1) Severance pay, also commonly referred to as dismissal wages, is a payment in addition to regular salaries and wages by contractors to workers whose employment is being involuntarily terminated. Payments for early retirement incentive plans are covered in paragraph (j)(7).

(2) Severance pay to be allowable must meet the general allowability criteria in subdivision (g)(2)(i) of this subsection, and, depending upon whether the severance is normal or abnormal, criteria in subdivision (g)(2)(ii) for normal severance pay or subdivision (g)(2)(iii) for abnormal severance pay also apply. In addition, paragraph (g)(3) of this subsection applies if the severance cost is for foreign nationals employed outside the United States.

(i) Severance pay is allowable only to the extent that, in each case, it is required by (A) law; (B) employer-employee agreement; (C) established policy that constitutes, in effect, an implied agreement on the contractor's part; or (D) circumstances of the particular employment. Payments made in the event of employment with a replacement contractor where continuity of employment with credit for prior length of service is preserved under substantially equal conditions of employment, or continued employment by the contractor at another facility, subsidiary, affiliate, or parent company of the contractor are not severance pay and are unallowable.

(ii) Actual normal turnover severance payments shall be allocated to all work performed in the contractor's plant, or where the contractor provides for accrual of pay for normal severances, that method will be acceptable if the amount of the accrual is reasonable in light of payments actually made for normal severances over a representative past period and if amounts accrued are allocated to all work performed in the contractor's plant.

(iii) Abnormal or mass severance pay is of such a conjectural nature that measurement of costs by means of an accrual will not achieve equity to both parties. Thus, accruals for this purpose are not allowable. However, the Government recognizes its obligation to participate, to the extent of its fair share, in any specific payment. Thus, allowability will be considered on a case-by-case basis.

(3) Notwithstanding the reference to geographical area in 31.205-6(b)(1), under 10 U.S.C. 2324(e)(1)(M) and 41 U.S.C. 256(e)(1)(M), the costs of severance payments to foreign nationals employed under a service contract performed outside the United States are unallowable to the extent that such payments exceed amounts typically paid to employees providing similar services in the same industry in the United States. Further, under 10 U.S.C. 2324(e)(1)(N) and 41 U.S.C. 256(e)(1)(N), all such costs of severance payments which are otherwise allowable are unallowable if the termination of employment of the foreign national is the result of the closing of, or the curtailment of activities at, a United States facility in that country at the request of the government of that country; this does not apply if the closing of a facility or curtailment of activities is made pursuant to a status-of-forces or other country-to-country agreement entered into with the government of that country before November 29, 1989. 10 U.S.C. 2324(e)(3) and 41 U.S.C. 256(e)(2) permit the head of the agency, or designee, to waive these cost allowability limitations under certain circumstances (see 37.113 and the solicitation provision at 52.237-8).

(h) Backpay. (1) Backpay resulting from violations of Federal labor laws or the Civil Rights Act of 1964. Backpay may result from a negotiated settlement, order, or court decree that resolves a violation of Federal labor laws or the Civil Rights Act of 1964. Such backpay falls into two categories: one requiring the contractor to pay employees additional compensation for work performed for which they were underpaid, and the other resulting from other violations, such as when the employee was improperly discharged, discriminated against, or other circumstances for which the backpay was not additional compensation for work performed. Backpay resulting from underpaid work is compensation for the work performed and is allowable. All other backpay resulting from violation of Federal labor laws or the Civil Rights Act of 1964 is unallowable.

(2) Other backpay. Backpay may also result from payments to employees (union and nonunion) for the difference in their past and current wage rates for working without a contract or labor agreement during labor management negotiations. Such backpay is allowable. Backpay to nonunion employees based upon results of union agreement negotiations is allowable only if--

(i) A formal agreement or understanding exists between management and the employees concerning these payments, or

(ii) An established policy or practice exists and is followed by the contractor so consistently as to imply, in effect, an agreement to make such payment.

(i) Compensation based on changes in the prices of corporate securities or corporate security ownership, such as stock options, stock appreciation rights, phantom stock plans, and junior stock conversions.

(1) Any compensation which is calculated, or valued, based on changes in the price of corporate securities is unallowable.

(2) Any compensation represented by dividend payments or which is calculated based on dividend payments is unallowable.

(3) If a contractor pays an employee in lieu of the employee receiving or exercising a right, option, or benefit which would have been unallowable under this paragraph (i), such payments are also unallowable.

(j) Pension costs. (1) A pension plan is a deferred compensation plan that is established and maintained by one or more employers to provide systematically for paying benefits to plan participants after their retirement, provided that the benefits are paid for life or are payable for life at the option of the employee. Additional benefits such as permanent and total disability and death payments and survivorship payments to beneficiaries of deceased employees may be treated as pension costs, provided the benefits are an integral part of the pension plan and meet all the criteria pertaining to pension costs.

(2) Pension plans are normally segregated into two types of plans: defined benefit or defined contribution pension plans. The cost of all defined benefit pension plans shall be measured, allocated, and accounted for in compliance with the provisions of 48 CFR 9904.412, Composition and Measurement of Pension Costs, and 48 CFR 9904.413, Adjustment and Allocation of Pension Cost. The costs of all defined contribution pension plans shall be measured, allocated, and accounted for in accordance with the provisions of 48 CFR 9904.412. Pension costs are allowable subject to the referenced standards and the cost limitations and exclusions set forth in subdivision (j)(2)(i) and in subparagraphs (j)(3) through (8) of this subsection.

(i) Except for unfunded pension plans as defined in 31.001, to be allowable in the current year, pension costs must be funded by the time set for filing of the Federal income tax return or any extension thereof. Pension costs assigned to the current year, but not funded by the tax return time, shall not be allowable in any subsequent year.

(ii) Pension payments must be reasonable in amount and be paid pursuant to (A) an agreement entered into in good faith between the contractor and employees before the work or services are performed and (B) the terms and conditions of the established plan. The cost of changes in pension plans which are discriminatory to the Government or are not intended to be applied consistently for all employees under similar circumstances in the future are not allowable.

(iii) Except as provided for early retirement benefits in subparagraph (j)(7) of this subsection, one-time-only pension supplements not available to all participants of the basic plan are not allowable as pension costs unless the supplemental benefits represent a separate pension plan and the benefits are payable for life at the option of the employee.

(iv) Increases in payments to previously retired plan participants covering cost-of-living adjustments are allowable if paid in accordance with a policy or practice consistently followed.

(3) Defined benefit pension plans. This subparagraph covers pension plans in which the benefits to be paid or the basis for determining such benefits are established in advance and the contributions are intended to provide the stated benefits. The cost limitations and exclusions pertaining to defined benefit plans are as follows:

(i)(A) Except for unfunded pension plans as defined in 31.001, normal costs of pension plans not funded in the year incurred, and all other components of pension costs (see 48 CFR 9904.412-40(a)(1)) assignable to the current accounting period but not funded during it, shall not be allowable in subsequent years (except that a payment made to a fund by the time set for filing the Federal income tax return or any extension thereof is considered to have been made during such taxable year). However, any part of a pension cost that is computed for a cost accounting period that is deferred pursuant to a waiver granted under the provisions of the Employee's Retirement Income Security Act of 1974 (ERISA) (see 48 CFR 9904.412-50(c)(3)), will be allowable in those future accounting periods in which the funding does occur. The allowability of these deferred contributions will be limited to the amounts that would have been allowed had the funding occurred in the year the costs would have been assigned except for the waiver.

(B) Allowable costs for unfunded pension plans, as defined in 31.001, are limited to the amount computed in accordance with 48 CFR 9904.412 and 48 CFR 9904.413.

(ii) Any amount paid or funded before the time it becomes assignable and allowable shall be applied to future years, in order of time, as if actually paid and deductible in those years. The interest earned on such premature funding, based on the valuation rate of return, may be excluded from future years' computations of pension costs in accordance with 48 CFR 9904.412-50(a)(7).

(iii) Increased pension costs caused by delay in funding beyond 30 days after each quarter of the year to which they are assignable are unallowable. If a composite rate is used for allocating pension costs between the segments of a company and if, because of differences in the timing of the funding by the segments, an inequity exists, allowable pension costs for each segment will be limited to that particular segment's calculation of pension costs as provided for in 48 CFR 9904.413-50(c)(5). Determination of unallowable costs shall be made in accordance with the actuarial method used in calculating pension costs.

(iv) Allowability of the cost of indemnifying the Pension Benefit Guaranty Corporation (PBGC) under ERISA Section 4062 or 4064 arising from terminating an employee deferred compensation plan will be considered on a case-by-case basis; provided that if insurance was required by the PBGC under ERISA Section 4023, it was so obtained and the indemnification payment is not recoverable under the insurance. Consideration under the foregoing circumstances will be primarily for the purpose of appraising the extent to which the indemnification payment is allocable to Government work. If a beneficial or other equitable relationship exists, the Government will participate, despite the requirements of 31.205-19(a)(3) and (b), in the indemnification payment to the extent of its fair share.

(v) Increased pension costs resulting from the withdrawal of assets from a pension fund and transfer to another employee benefit plan fund are unallowable except to the extent authorized by an advance agreement. The advance agreement shall:

(A) State the amount of the Government's equitable share in the gross amount withdrawn; and

(B) Provide that the Government receive a credit equal to the amount of the Government's equitable share of the gross withdrawal. If a transfer is made without such an agreement, paragraph (j)(4) of this subsection will apply to the transfer as a constructive withdrawal and receipt of the funds by the contractor.

(4) Termination of defined benefit pension plans. When excess or surplus assets revert to the contractor as a result of termination of a defined benefit pension plan, or such assets are constructively received by it for any reason, the contractor shall make a refund or give a credit to the Government for its equitable share of the gross amount withdrawn. The Government's equitable share shall reflect the Government's participation in pension costs through those contracts for which cost or pricing data (see 15.403-4) were submitted or which are subject to Subpart 31.2.

(5) Defined contribution pension plans. This subparagraph covers those pension plans in which the contributions to be made are established in advance and the level of benefits is determined by the contributions made. It also covers profit sharing, savings plans, and other such plans provided the plans fall within the definition of a pension plan in subparagraph (j)(1) of this subsection.

(i) The pension cost assignable to a cost accounting period is the net contribution required to be made for that period after taking into account dividends and other credits, where applicable. However, any portion of pension cost computed for a cost accounting period that is deferred pursuant to a waiver granted under the provisions of ERISA (see 48 CFR 9904.412-50(c)(3)) will be allowable in those future accounting periods when the funding does occur. The allowability of these deferred contributions will be limited to the amounts that would have been allowed had the funding been made in the year the costs would have been assigned except for the waiver.

(ii) Any amount paid or funded to the trust before the time it becomes assignable and allowable shall be applied to future years, in order of time, as if actually paid and deductible in such years.

(iii) The provisions of subdivision (j)(3)(iv) of this subsection concerning payments to PBGC apply to defined contribution plans.

(6) Pension plans using pay-as-you-go methods. [Reserved]

(7) Early retirement incentive plans. An early retirement incentive plan is a plan under which employees receive a bonus or incentive, over and above the requirement of the basic pension plan, to retire early. These plans normally are not applicable to all participants of the basic plan and do not represent life income settlements, and as such would not qualify as pension costs. However, for contract costing purposes, early retirement incentive payments are allow-able subject to the pension cost criteria contained in subdivisions (j)(3)(i) through (iv) provided--

(i) The costs are accounted for and allocated in accordance with the contractor's system of accounting for pension costs;

(ii) The payments are made in accordance with the terms and conditions of the contractor's plan;

(iii) The plan is applied only to active employees. The cost of extending the plan to employees who retired or were terminated before the adoption of the plan is unallowable; and

(iv) The total of the incentive payments to any employee may not exceed the amount of the employee's annual salary for the previous fiscal year before the employee's retirement.

(8) Employee stock ownership plans (ESOP). (i) An ESOP is an individual stock bonus plan designed specifically to invest in the stock of the employer corporation. The contractor's contributions to an Employee Stock Ownership Trust (ESOT) may be in the form of cash, stock, or property. Costs of ESOP's are allowable subject to the following conditions:

(A) Contributions by the contractor in any one year may not exceed 15 percent (25 percent when a money purchase plan is included) of salaries and wages of employees participating in the plan in any particular year.

(B) The contribution rate (ratio of contribution to salaries and wages of participating employees) may not exceed the last approved contribution rate except when approved by the contracting officer based upon justification provided by the contractor. When no contribution was made in the previous year for an existing ESOP, or when a new ESOP is first established, and the contractor proposes to make a contribution in the current year, the contribution rate shall be subject to the contracting officer's approval.

(C) When a plan or agreement exists wherein the liability for the contribution can be compelled for a specific year, the expense associated with that liability is assignable only to that period. Any portion of the contribution not funded by the time set for filing of the Federal income tax return for that year or any extension thereof shall not be allowable in subsequent years.

(D) When a plan or agreement exists wherein the liability for the contribution cannot be compelled, the amount contributed for any year is assignable to that year provided the amount is funded by the time set for filing of the Federal income tax return for that year.

(E) When the contribution is in the form of stock, the value of the stock contribution shall be limited to the fair market value of the stock on the date that title is effectively transferred to the trust. Cash contributions shall be allowable only when the contractor furnishes evidence satisfactory to the contracting officer demonstrating that stock purchases by the ESOT are or will be at a fair market price; e.g., makes arrangements with the trust permitting the contracting officer to examine purchases of stock by the trust to determine that prices paid are at fair market value. When excessive prices are paid, the amount of the excess will be credited to the same indirect cost pools that were charged for the ESOP contributions in the year in which the stock purchase occurs. However, when the trust purchases the stock with borrowed funds which will be repaid over a period of years by cash contributions from the contractor to the trust, the excess price over fair market value shall be credited to the indirect cost pools pro rata over the period of years during which the contractor contributes the cash used by the trust to repay the loan. When the fair market value of unissued stock or stock of a closely held corporation is not readily determinable, the valuation will be made on a case-by-case basis taking into consideration the guidelines for valuation used by the IRS.

(ii) Amounts contributed to an ESOP arising from either--

(A) An additional investment tax credit (see 1975 Tax Reduction Act--TRASOP's); or

(B) A payroll-based tax credit (see Economic Recovery Tax Act of 1981) are unallowable.

(iii) The requirements of subdivision (j)(3)(ii) of this subsection are applicable to Employee Stock Ownership Plans.

(k) Deferred compensation. (1) Deferred compensation is an award given by an employer to compensate an employee in a future cost accounting period or periods for services rendered in one or more cost accounting periods before the date of receipt of compensation by the employee. Deferred compensation does not include the amount of year-end accruals for salaries, wages, or bonuses that are paid within a reasonable period of time after the end of a cost accounting period. Subject to 31.205-6(a), deferred awards are allowable when they are based on current or future services. Awards made in periods subsequent to the period when the work being remunerated was performed are not allowable.

(2) The costs of deferred awards shall be measured, allocated, and accounted for in compliance with the provisions of 48 CFR 9904.415, Accounting for the Cost of Deferred Compensation.

(3) Deferred compensation payments to employees under awards made before the effective date of 48 CFR 9904.415 are allowable to the extent they would have been allowable under prior acquisition regulations.

(l) Compensation incidental to business acquisitions. The following costs are unallowable:

(1) Payments to employees under agreements in which they receive special compensation, in excess of the contractor's normal severance pay practice, if their employment terminates following a change in the management control over, or ownership of, the contractor or a substantial portion of its assets.

(2) Payments to employees under plans introduced in connection with a change (whether actual or prospective) in the management control over, or ownership of, the contractor or a substantial portion of its assets in which those employees receive special compensation, which is contingent upon the employee remaining with the contractor for a specified period of time.

(m) Fringe benefits. (1) Fringe benefits are allowances and services provided by the contractor to its employees as compensation in addition to regular wages and salaries. Fringe benefits include, but are not limited to, the cost of vacations, sick leave, holidays, military leave, employee insurance, and supplemental unemployment benefit plans. Except as provided otherwise in Subpart 31.2, the costs of fringe benefits are allowable to the extent that they are reasonable and are required by law, employer-employee agreement, or an established policy of the contractor.

(2) That portion of the cost of company-furnished automobiles that relates to personal use by employees (including transportation to and from work) is unallowable regardless of whether the cost is reported as taxable income to the employees (see 31.205-46(f)).

(n) Employee rebate and purchase discount plans. Rebates and purchase discounts, in whatever form, granted to employees on products or services produced by the contractor or affiliates are unallowable.

(o) Postretirement benefits other than pensions (PRB). (1) PRB covers all benefits, other than cash benefits and life insurance benefits paid by pension plans, provided to employees, their beneficiaries, and covered dependents during the period following the employees' retirement. Benefits encompassed include, but are not limited to, postretirement health care; life insurance provided outside a pension plan; and other welfare benefits such as tuition assistance, day care, legal services, and housing subsidies provided after retirement.

(2) To be allowable, PRB costs must be reasonable and incurred pursuant to law, employer-employee agreement, or an established policy of the contractor. In addition, to be allowable, PRB costs must also be calculated in accordance with paragraphs (o)(2)(i), (ii), or (iii) of this section.

(i) Cash basis. Cost recognized as benefits when they are actually provided, must be paid to an insurer, provider, or other recipient for current year benefits or premiums.

(ii) Terminal funding. If a contractor elects a terminal-funded plan, it does not accrue PRB costs during the working lives of employees. Instead, it accrues and pays the entire PRB liability to an insurer or trustee in a lump sum upon the termination of employees (or upon conversion to such a terminal-funded plan) to establish and maintain a fund or reserve for the sole purpose of providing PRB to retirees. The lump sum is allowable if amortized over a period of 15 years.

(iii) Accrual basis. Accrual costing other than terminal funding must be measured and assigned according to Generally Accepted Accounting Principles and be paid to an insurer or trustee to establish and maintain a fund or reserve for the sole purpose of providing PRB to retirees. The accrual must also be calculated in accordance with generally accepted actuarial principles and practices as promulgated by the Actuarial Standards Board.

(3) To be allowable, costs must be funded by the time set for filing the Federal income tax return or any extension thereof. PRB costs assigned to the current year, but not funded or otherwise liquidated by the tax return time, shall not be allowable in any subsequent year.

(4) Increased PRB costs caused by delay in funding beyond 30 days after each quarter of the year to which they are assignable are unallowable.

(5) Costs of postretirement benefits in subdivision (o)(2)(iii) of this subsection attributable to past service ("transition obligation") as defined in Financial Accounting Standards Board Statement 106, paragraph 110, are allowable subject to the following limitation: The allowable amount of such costs assignable to a contractor fiscal year cannot exceed the amount of such costs which would be assigned to that contractor fiscal year under the delayed recognition methodology described in paragraphs 112 and 113 of Statement 106.

(6) The Government shall receive an equitable share of any amount of previously funded PRB costs which revert or inure to the contractor. Such equitable share shall reflect the Government's previous participation in PRB costs through those contracts for which certified cost or pricing data were required or which were subject to Subpart 31.2.

(p) Limitation on allowability of compensation for certain contractor personnel. (1) For contracts awarded during fiscal year 1997, costs incurred from October 1, 1996, through September 30, 1997, for compensation of an officer in a senior management position that exceed $250,000 per year are unallowable (Section 809 of Public Law 104-201).

(2) As used in this paragraph:

(i) "Compensation" means--

(A) The total amount of taxable wages paid to the employee for the year concerned; plus

(B) The total amount of elective deferred compensation earned by the employee in the year concerned.

(ii) "Officer in a senior management position" means--

(A) The contractor's Chief Executive Officer (CEO) or any individual acting in a similar capacity;

(B) The contractor's four most highly compensated officers in senior management positions, other than the CEO; and

(C) If the contractor is organizationally subdivided into intermediate home offices and/or segments, the five most highly compensated individuals in senior management positions at each such intermediate home office and/or segment.

31.205-7 Contingencies.

(a) "Contingency," as used in this subpart, means a possible future event or condition arising from presently known or unknown causes, the outcome of which is indeterminable at the present time.

(b) Costs for contingencies are generally unallowable for historical costing purposes because such costing deals with costs incurred and recorded on the contractor's books. However, in some cases, as for example, terminations, a contingency factor may be recognized when it is applicable to a past period to give recognition to minor unsettled factors in the interest of expediting settlement.

(c) In connection with estimates of future costs, contingencies fall into two categories:

(1) Those that may arise from presently known and existing conditions, the effects of which are foreseeable within reasonable limits of accuracy; e.g., anticipated costs of rejects and defective work. Contingencies of this category are to be included in the estimates of future costs so as to provide the best estimate of performance cost.

(2) Those that may arise from presently known or unknown conditions, the effect of which cannot be measured so precisely as to provide equitable results to the contractor and to the Government; e.g., results of pending litigation. Contingencies of this category are to be excluded from cost estimates under the several items of cost, but should be disclosed separately (including the basis upon which the contingency is computed) to facilitate the negotiation of appropriate contractual coverage. (See, for example, 31.205-6(g), 31.205-19, and 31.205-24.)

31.205-8 Contributions or donations.

Contributions or donations, including cash, property and services, regardless of recipient, are unallowable, except as provided in 31.205-1(e)(3).

31.205-9 [Reserved]

31.205-10 Cost of money.

(a) Facilities capital cost of money--(1) General. (i) Facilities capital cost of money (cost of capital committed to facilities) is an imputed cost determined by applying a cost-of-money rate to facilities capital employed in contract performance. A cost-of-money rate is uniformly imputed to all contractors (see subdivision (a)(1)(ii) of this subsection). Capital employed is determined without regard to whether its source is equity or borrowed capital. The resulting cost of money is not a form of interest on borrowings (see 31.205-20).

(ii) 48 CFR 9904.414, Cost of Money as an Element of the Cost of Facilities Capital, establishes criteria for measuring and allocating, as an element of contract cost, the cost of capital committed to facilities. Cost-of-money factors are developed on Form CASB-CMF, broken down by overhead pool at the business unit, using--

(A) Business-unit facilities capital data,

(B) Overhead allocation base data, and

(C) The cost-of-money rate, which is based on interest rates specified by the Secretary of the Treasury under Public Law 92-41.

(2) Allowability. Whether or not the contract is otherwise subject to CAS, facilities capital cost of money is allowable if--

(i) The contractor's capital investment is measured, allocated to contracts, and costed in accordance with 48 CFR 9904.414;

(ii) The contractor maintains adequate records to demonstrate compliance with this standard;

(iii) The estimated facilities capital cost of money is specifically identified or proposed in cost proposals relating to the contract under which this cost is to be claimed; and

(iv) The requirements of 31.205-52, which limit the allowability of facilities capital cost of money, are observed.

(3) Accounting. The facilities capital cost of money need not be entered on the contractor's books of account. However, the contractor shall--

(i) Make a memorandum entry of the cost, and

(ii) Maintain, in a manner that permits audit and verification, all relevant schedules, cost data, and other data necessary to support the entry fully.

(4) Payment. Facilities capital cost of money that is--

(i) Allowable under subparagraph (2) of this subsection; and

(ii) Calculated, allocated, and documented in accordance with this cost principle shall be an "incurred cost" for reimbursement purposes under applicable cost-reimbursement contracts and for progress payment purposes under fixed-price contracts.

(5) The cost of money resulting from including asset valuations resulting from business combinations in the facilities capital employed base is unallowable (see 31.205-52).

(b) Cost of money as an element of the cost of capital assets under construction--(1) General. (i) Cost of money as an element of the cost of capital assets under construction is an imputed cost determined by applying a cost-of-money rate to the investment in tangible and intangible capital assets while they are being constructed, fabricated, or developed for a contractor's own use. Capital employed is determined without regard to whether its source is equity or borrowed capital. The resulting cost of money is not a form of interest on borrowing (see 31.205-20).

(ii) 48 CFR 9904.417, Cost of Money as an Element of the Cost of Capital Assets Under Construction, establishes criteria for measuring and allocating, as an element of contract cost, the cost of capital committed to capital assets under construction, fabrication, or development.

(2) Allowability. (i) Whether or not the contract is otherwise subject to CAS, and except as specified in subdivision (ii) of this section, the cost of money for capital assets under construction, fabrication, or development is allowable if--

(A) The cost of money is calculated, allocated to contracts, and costed in accordance with 48 CFR 9904.417;

(B) The contractor maintains adequate records to demonstrate compliance with this standard;

(C) The cost of money for tangible capital assets is included in the capitalized cost that provides the basis for allowable depreciation costs, or, in the case of intangible capital assets, the cost of money is included in the cost of those assets for which amortization costs are allowable; and

(D) The requirements of 31.205-52, which limit the allowability of cost of money for capital assets under construction, fabrication, or development, are observed.

(ii) Actual interest cost in lieu of the calculated imputed cost of money for capital assets under construction, fabrication, or development is unallowable.

(3) Accounting. The cost of money for capital assets under construction need not be entered on the contractor's books of account. However, the contractor shall (i) make a memorandum entry of the cost and (ii) maintain, in a manner that permits audit and verification, all relevant schedules, cost data, and other data necessary to support the entry fully.

(4) Payment. The cost of money for capital assets under construction that is allowable under subparagraph (2) above of this cost principle shall be an "incurred cost" for reimbursement purposes under applicable cost-reimbursement contracts and for progress payment purposes under fixed-price contracts.

31.205-11 Depreciation.

(a) Depreciation is a charge to current operations which distributes the cost of a tangible capital asset, less estimated residual value, over the estimated useful life of the asset in a systematic and logical manner. It does not involve a process of valuation. Useful life refers to the prospective period of economic usefulness in a particular contractor's operations as distinguished from physical life; it is evidenced by the actual or estimated retirement and replacement practice of the contractor.

(b) Contractors having contracts subject to 48 CFR 9904.409, Depreciation of Tangible Capital Assets, must adhere to the requirement of that standard for all fully CAS-covered contracts and may elect to adopt the standard for all other contracts. All requirements of 48 CFR 9904.409 are applicable if the election is made, and its requirements supersede any conflicting requirements of this cost principle. Once electing to adopt 48 CFR 9904.409 for all contracts, contractors must continue to follow it until notification of final acceptance of all deliverable items on all open negotiated Government contracts. Paragraphs (c) through (e) below apply to contracts to which 48 CFR 9904.409 is not applied.

(c) Normal depreciation on a contractor's plant, equipment, and other capital facilities is an allowable contract cost, if the contractor is able to demonstrate that it is reasonable and allocable (but see paragraph (i) of this section).

(d) Depreciation shall be considered reasonable if the contractor follows policies and procedures that are--

(1) Consistent with those followed in the same cost center for business other than Government;

(2) Reflected in the contractor's books of accounts and financial statements; and

(3) Both used and acceptable for Federal income tax purposes.

(e) When the depreciation reflected on a contractor's books of accounts and financial statements differs from that used and acceptable for Federal income tax purposes, reimbursement shall be based on the asset cost amortized over the estimated useful life of the property using depreciation methods (straight line, sum of the years' digits, etc.) acceptable for income tax purposes. Allowable depreciation shall not exceed the amounts used for book and statement purposes and shall be determined in a manner consistent with the depreciation policies and procedures followed in the same cost center on non-Government business (but see paragraph (o) of this subsection).

(f) Depreciation for reimbursement purposes in the case of tax-exempt organizations shall be determined on the basis described in paragraph (e) of this section.

(g) Special considerations are required for assets acquired before the effective date of this cost principle if, on that date, the undepreciated balance of these assets resulting from depreciation policies and procedures used previously for Government contracts and subcontracts is different from the undepreciated balance on the books and financial statements. The undepreciated balance for contract cost purposes shall be depreciated over the remaining life using the methods and lives followed for book purposes. The aggregate depreciation of any asset allowable after the effective date of this 31.205-11 shall not exceed the cost basis of the asset less any depreciation allowed or allowable under prior acquisition regulations.

(h) Depreciation should usually be allocated to the contract and other work as an indirect cost. The amount of depreciation allowed in any accounting period may, consistent with the basic objectives in paragraph (a) above, vary with volume of production or use of multishift operations.

(i) In the case of emergency facilities covered by certificates of necessity, a contractor may elect to use normal depreciation without requesting a determination of "true depreciation," or may elect to use either normal or "true depreciation" after a determination of "true depreciation" has been made by an Emergency Facilities Depreciation Board (EFDB). The method elected must be followed consistently throughout the life of the emergency facility. When an election is made to use normal depreciation, the criteria in paragraphs (c), (d), (e), and (f) of this section shall apply for both the emergency period and the post-emergency period. When an election is made to use "true depreciation", the amount allowable as depreciation--

(1) With respect to the emergency period (five years), shall be computed in accordance with the determination of the EFDB and allocated rateably over the full five year emergency period; provided no other allowance is made which would duplicate the factors, such as extraordinary obsolescence, covered by the Board's determination; and

(2) After the end of the emergency period, shall be computed by distributing the remaining undepreciated portion of the cost of the emergency facility over the balance of its useful life provided the remaining undepreciated portion of such cost shall not include any amount of unrecovered "true depreciation."

(j) No depreciation, rental, or use charge shall be allowed on property acquired at no cost from the Government by the contractor or by any division, subsidiary, or affiliate of the contractor under common control.

(k) The depreciation on any item which meets the criteria for allowance at a "price" under 31.205-26(e) may be based on that price, provided the same policies and procedures are used for costing all business of the using division, subsidiary, or organization under common control.

(l) No depreciation or rental shall be allowed on property fully depreciated by the contractor or by any division, subsidiary, or affiliate of the contractor under common control. However, a reasonable charge for using fully depreciated property may be agreed upon and allowed (but see 31.109(h)(2)). In determining the charge, consideration shall be given to cost, total estimated useful life at the time of negotiations, effect of any increased maintenance charges or decreased efficiency due to age, and the amount of depreciation previously charged to Government contracts or subcontracts.

(m) 48 CFR 9904.404, Capitalization of Tangible Assets, applies to assets acquired by a "capital lease" as defined in Statement of Financial Accounting Standard No. 13 (FAS-13), Accounting for Leases, issued by the Financial Accounting Standards Board (FASB). Compliance with 48 CFR 9904.404 and FAS-13 requires that such leased assets (capital leases) be treated as purchased assets; i.e., be capitalized and the capitalized value of such assets be distributed over their useful lives as depreciation charges, or over the leased life as amortization charges as appropriate. Assets whose leases are classified as capital leases under FAS-13 are subject to the requirements of 31.205-11 while assets acquired under leases classified as operating leases are subject to the requirements on rental costs in 31.205-36. The standards of financial accounting and reporting prescribed by FAS-13 are incorporated into this principle and shall govern its application, except as provided in subparagraphs (1), (2), and (3) of this paragraph.

(1) Rental costs under a sale and leaseback arrangement shall be allowable up to the amount that would have been allowed had the contractor retained title to the property.

(2) Capital leases, as defined in FAS-13, for all real and personal property, between any related parties are subject to the requirements of this subparagraph 31.205-11(m). If it is determined that the terms of the lease have been significantly affected by the fact that the lessee and lessor are related, depreciation charges shall not be allowed in excess of those which would have occurred if the lease contained terms consistent with those found in a lease between unrelated parties.

(3) Assets acquired under leases that the contractor must capitalize under FAS-13 shall not be treated as purchased assets for contract purposes if the leases are covered by 31.205-36(b)(4).

(n) Whether or not the contract is otherwise subject to CAS, the requirements of 31.205-52, which limit the allowability of depreciation, shall be observed.

(o) In the event of a write-down from carrying value to fair value as a result of impairments caused by events or changes in circumstances, allowable depreciation of the impaired assets shall be limited to the amounts that would have been allowed had the assets not been written down (see 31.205-16(g)). However, this does not preclude a change in depreciation resulting from other causes such as permissible changes in estimates of service life, consumption of services, or residual value.

31.205-12 Economic planning costs.

(a) This category includes costs of generalized long-range management planning that is concerned with the future overall development of the contractor's business and that may take into account the eventual possibility of economic dislocations or fundamental alterations in those markets in which the contractor currently does business Economic planning costs do not include organization or reorganization costs covered by 31.205-27.

(b) Economic planning costs are allowable as indirect costs to be properly allocated.

(c) Research and development and engineeri